Todd Lindquist, Corps of Engineers announced today at a Burleigh County Commission meeting that the Corps of Engineers has updated the schedule of releases from Garrison Dam.
May 30 85,000 cfs
June 4 90,000 cfs
June 6 95,000 cfs
June 7 100,000 cfs
Planned scheduled releases are subject to change based on changing reservoir and river conditions.
Upon being provided this information Mayor Warford said that “The Army Corps of Engineers is on track and assures citizens that the construction schedule for the levees will be met. They are working on the most critical areas and remain within their schedule for completion.”